Nidera Terminal
START OF WORK: 1983
TIME: Two years
WORK: Transit Terminal
TYPE: Turnkey work.
LOCATION: Nidera
INVESTMENT: 25,000,000 dollars
Implementation
MATERIAL: 7,500 m³ of concrete were used
IRON: 3500 tons of iron in profiles for metal structures and transport equipment
Characteristic
- LOAD RATE: Grains 1200 tn / h – Byproducts 800 tn / h – Oils 35.000 tn / h
- FRETWORK: 32 feet.
- DOCK: Four mooring dolphins and two mooring dolphins. Between extreme dolphins there is 200 m.
- Mechanizations and engines.
-
Storage system by cylindrical silos conical bottom and cell silos: capacity 300,000 tons.
- Aspiration and powder injection system
- System of interlock of reception and boarding by PLC
- Continuous flow loading balance.
- Double reception scale and three dump platforms, for complete equipment, of 15 cycles / hour each.
-
Area for 350 trucks
Storage capacity
GRAINS: 570,000 tn
SUBPRODUCTS: 45,000 tn
OILS: 35,000 tn

Description
The dock allows the mooring of vessels whose length does not exceed 270 m. It can operate simultaneously a grain ship in the dock and an oil vessel in first swath. It has six reinforced concrete dolphins, with one bite in each one (two outside the docking front towards the coast and four are with wooden and rubber fenders supported by chains). Load up to 32 feet. Fire Fighting System has a monitor and an extinguisher on the main gangway. . It is suitable for the loading of cereals, by-products and oleaginous oils. Load capacity 1200 tn / h. Barges can operate inside the dock.