Nidera Terminal

START OF WORK: 1983

TIME: Two years

WORK: Transit Terminal

TYPE: Turnkey work.

LOCATION: Nidera

INVESTMENT: 25,000,000 dollars

Implementation

MATERIAL: 7,500 m³ of concrete were used

IRON: 3500 tons of iron in profiles for metal structures and transport equipment

Characteristic

  • LOAD RATE: Grains 1200 tn / h – Byproducts 800 tn / h – Oils 35.000 tn / h
  • FRETWORK: 32 feet.
  • DOCK: Four mooring dolphins and two mooring dolphins. Between extreme dolphins there is 200 m.
  • Mechanizations and engines.
  • Storage system by cylindrical silos conical bottom and cell silos: capacity 300,000 tons.

  • Aspiration and powder injection system
  • System of interlock of reception and boarding by PLC
  • Continuous flow loading balance.
  • Double reception scale and three dump platforms, for complete equipment, of 15 cycles / hour each.
  • Area for 350 trucks

Storage capacity

GRAINS: 570,000 tn

SUBPRODUCTS: 45,000 tn

OILS: 35,000 tn

Description

The dock allows the mooring of vessels whose length does not exceed 270 m. It can operate simultaneously a grain ship in the dock and an oil vessel in first swath. It has six reinforced concrete dolphins, with one bite in each one (two outside the docking front towards the coast and four are with wooden and rubber fenders supported by chains). Load up to 32 feet. Fire Fighting System has a monitor and an extinguisher on the main gangway. . It is suitable for the loading of cereals, by-products and oleaginous oils. Load capacity 1200 tn / h. Barges can operate inside the dock.